AEC Master Program & Deliverables

KMP-2026-04Kensington Mews Contemporary Pavilion & Residences
Client: Cadogan Heritage Estates Ltd.•Handover: 30 Nov 2027
Local Mode
RIBA Plan of Work Hierarchy
8 Stages • 15 Tasks
0
Stage 0: Strategic Definition
100%
Site Feasibility & Massing Assessment
01 Sep – 18 Sep
ApprovedEleanor Vance, RIBA100%
Client Strategic Brief Approval
22 Sep – 25 Sep
ApprovedLord Edward Harrington100%
1
Stage 1: Preparation & Briefing
100%
Topographical & Measured Building Survey
26 Sep – 10 Oct
ApprovedMarcus Chen100%
Project Brief Freeze & Sustainability Charter
20 Oct – 24 Oct
ApprovedEleanor Vance, RIBA100%
2
Stage 2: Concept Design
585%
Architectural Concept Drawings & Plans
25 Oct – 20 NovA-100 (+3)
In ProgressMarcus Chen90%
Structural & MEP Systems Strategy
10 Nov – 05 DecS-100
In ProgressSamira Hadid, CEng MICE80%
Stage 2 Client Concept Signoff Gate
10 Dec – 15 Dec
ReviewLord Edward Harrington75%
3
Stage 3: Spatial Coordination
125%
Spatial Coordination & 3D BIM Model Federation
16 Dec – 30 JanA-301
In ProgressMarcus Chen30%
Statutory Gate: Planning Permission Submission
01 Feb – 15 Feb
PendingEleanor Vance, RIBA10%
Stage 3 Freeze & Design Freeze Milestone
10 Mar – 15 Mar
PendingLord Edward Harrington0%
4
Stage 4: Technical Design
10%
Building Regulations & NBS Chorus Specifications
16 Mar – 15 MaySPEC-01
PendingMarcus Chen0%
Statutory Gate: BSA Gateway 2 Application
16 May – 15 Jun
PendingEleanor Vance, RIBA0%
5
Stage 5: Manufacturing & Construction
0%
Main Contractor Site Mobilization & Substructure
01 Jul – 15 Sep
PendingMarcus Chen0%
Roof Weathertight Envelope & Topping Out
30 Sep – 15 Oct
PendingEleanor Vance, RIBA0%
6
Stage 6: Handover
0%
Practical Completion & Golden Thread Handover
16 Oct – 15 Nov
PendingLord Edward Harrington0%
7
Stage 7: Use
0%
No matching tasks in this stage
0
1
2
3
4
5
6
7
6m
August 2026
September 2026
October 2026
November 2026
December 2026
January 2027
February 2027
March 2027
April 2027
May 2027
June 2027
July 2027
August 2027
September 2027
October 2027
November 2027
December 2027
January 2028
W3203 Aug - 09 Aug
W3310 Aug - 16 Aug
W3417 Aug - 23 Aug
W3524 Aug - 30 Aug
W3631 Aug - 06 Sep
W3707 Sep - 13 Sep
W3814 Sep - 20 Sep
W3921 Sep - 27 Sep
W4028 Sep - 04 Oct
W4105 Oct - 11 Oct
W4212 Oct - 18 Oct
W4319 Oct - 25 Oct
W4426 Oct - 01 Nov
W4502 Nov - 08 Nov
W4609 Nov - 15 Nov
W4716 Nov - 22 Nov
W4823 Nov - 29 Nov
W4930 Nov - 06 Dec
W5007 Dec - 13 Dec
W5114 Dec - 20 Dec
W5221 Dec - 27 Dec
W128 Dec - 03 Jan
W204 Jan - 10 Jan
W311 Jan - 17 Jan
W418 Jan - 24 Jan
W525 Jan - 31 Jan
W601 Feb - 07 Feb
W708 Feb - 14 Feb
W815 Feb - 21 Feb
W922 Feb - 28 Feb
W1001 Mar - 07 Mar
W1108 Mar - 14 Mar
W1215 Mar - 21 Mar
W1322 Mar - 28 Mar
W1429 Mar - 04 Apr
W1505 Apr - 11 Apr
W1612 Apr - 18 Apr
W1719 Apr - 25 Apr
W1826 Apr - 02 May
W1903 May - 09 May
W2010 May - 16 May
W2117 May - 23 May
W2224 May - 30 May
W2331 May - 06 Jun
W2407 Jun - 13 Jun
W2514 Jun - 20 Jun
W2621 Jun - 27 Jun
W2728 Jun - 04 Jul
W2805 Jul - 11 Jul
W2912 Jul - 18 Jul
W3019 Jul - 25 Jul
W3126 Jul - 01 Aug
W3202 Aug - 08 Aug
W3309 Aug - 15 Aug
W3416 Aug - 22 Aug
W3523 Aug - 29 Aug
W3630 Aug - 05 Sep
W3706 Sep - 12 Sep
W3813 Sep - 19 Sep
W3920 Sep - 26 Sep
W4027 Sep - 03 Oct
W4104 Oct - 10 Oct
W4211 Oct - 17 Oct
W4318 Oct - 24 Oct
W4425 Oct - 31 Oct
W4501 Nov - 07 Nov
W4608 Nov - 14 Nov
W4715 Nov - 21 Nov
W4822 Nov - 28 Nov
W4929 Nov - 05 Dec
W5006 Dec - 12 Dec
W5113 Dec - 19 Dec
W5220 Dec - 26 Dec
W127 Dec - 02 Jan
W203 Jan - 09 Jan
W310 Jan - 16 Jan
TODAY
Stage 0: Strategic Definition
100%
Site Feasibility & Massing Assessment
100%
Client Strategic Brief Approval
100%
Stage 1: Preparation & Briefing
100%
Topographical & Measured Building Survey
100%
Project Brief Freeze & Sustainability Charter
Stage 2: Concept Design
85%
Architectural Concept Drawings & PlansA-100
90%
Structural & MEP Systems StrategyS-100
80%
Stage 2 Client Concept Signoff Gate
75%
Stage 3: Spatial Coordination
25%
Spatial Coordination & 3D BIM Model FederationA-301
30%
Statutory Gate: Planning Permission Submission
10%
Stage 3 Freeze & Design Freeze Milestone
Stage 4: Technical Design
0%
Building Regulations & NBS Chorus SpecificationsSPEC-01
0%
Statutory Gate: BSA Gateway 2 Application
0%
Stage 5: Manufacturing & Construction
0%
Main Contractor Site Mobilization & Substructure
0%
Roof Weathertight Envelope & Topping Out
Stage 6: Handover
0%
Practical Completion & Golden Thread Handover
0%
Stage 7: Use
0%