AEC Master Program & Deliverables
KMP-2026-04
Kensington Mews Contemporary Pavilion & Residences
Client: Cadogan Heritage Estates Ltd.
•
Handover: 30 Nov 2027
Master Program Progress
39% Complete
Drawing Sheets
2
/ 7 Approved
Local Mode
+4
Vlad Condrea
Admin
All Items
Statutory Gates
Client Signoffs
Milestones
Expand All
Collapse All
Days
Weeks
Months
Preset: RIBA 0–7
Export Schedule
Add Task / Gate
RIBA Plan of Work Hierarchy
8 Stages • 15 Tasks
0
Stage 0: Strategic Definition
01 Sep – 25 Sep
100%
Site Feasibility & Massing Assessment
01 Sep – 18 Sep
Approved
100%
Client Strategic Brief Approval
22 Sep – 25 Sep
Approved
100%
1
Stage 1: Preparation & Briefing
26 Sep – 24 Oct
100%
Topographical & Measured Building Survey
26 Sep – 10 Oct
Approved
100%
Project Brief Freeze & Sustainability Charter
20 Oct – 24 Oct
Approved
100%
2
Stage 2: Concept Design
25 Oct – 15 Dec
5
85%
Architectural Concept Drawings & Plans
25 Oct – 20 Nov
A-100 (+3)
In Progress
90%
Structural & MEP Systems Strategy
10 Nov – 05 Dec
S-100
In Progress
80%
Stage 2 Client Concept Signoff Gate
10 Dec – 15 Dec
Review
75%
3
Stage 3: Spatial Coordination
16 Dec – 15 Mar
1
25%
Spatial Coordination & 3D BIM Model Federation
16 Dec – 30 Jan
A-301
In Progress
30%
Statutory Gate: Planning Permission Submission
01 Feb – 15 Feb
Pending
10%
Stage 3 Freeze & Design Freeze Milestone
10 Mar – 15 Mar
Pending
0%
4
Stage 4: Technical Design
16 Mar – 30 Jun
1
0%
Building Regulations & NBS Chorus Specifications
16 Mar – 15 May
SPEC-01
Pending
0%
Statutory Gate: BSA Gateway 2 Application
16 May – 15 Jun
Pending
0%
5
Stage 5: Manufacturing & Construction
01 Jul – 15 Oct
0%
Main Contractor Site Mobilization & Substructure
01 Jul – 15 Sep
Pending
0%
Roof Weathertight Envelope & Topping Out
30 Sep – 15 Oct
Pending
0%
6
Stage 6: Handover
16 Oct – 15 Nov
0%
Practical Completion & Golden Thread Handover
16 Oct – 15 Nov
Pending
0%
7
Stage 7: Use
16 Nov – 31 Dec
0%
No matching tasks in this stage
Minimap
0
Strategic Definition
1
Preparation & Briefing
2
Concept Design
3
Spatial Coordination
4
Technical Design
5
Manufacturing & Construction
6
Handover
7
Use
6m
Fit All
August 2026
September 2026
October 2026
November 2026
December 2026
January 2027
February 2027
March 2027
April 2027
May 2027
June 2027
July 2027
August 2027
September 2027
October 2027
November 2027
December 2027
January 2028
W32
03 Aug - 09 Aug
W33
10 Aug - 16 Aug
W34
17 Aug - 23 Aug
W35
24 Aug - 30 Aug
W36
31 Aug - 06 Sep
W37
07 Sep - 13 Sep
W38
14 Sep - 20 Sep
W39
21 Sep - 27 Sep
W40
28 Sep - 04 Oct
W41
05 Oct - 11 Oct
W42
12 Oct - 18 Oct
W43
19 Oct - 25 Oct
W44
26 Oct - 01 Nov
W45
02 Nov - 08 Nov
W46
09 Nov - 15 Nov
W47
16 Nov - 22 Nov
W48
23 Nov - 29 Nov
W49
30 Nov - 06 Dec
W50
07 Dec - 13 Dec
W51
14 Dec - 20 Dec
W52
21 Dec - 27 Dec
W1
28 Dec - 03 Jan
W2
04 Jan - 10 Jan
W3
11 Jan - 17 Jan
W4
18 Jan - 24 Jan
W5
25 Jan - 31 Jan
W6
01 Feb - 07 Feb
W7
08 Feb - 14 Feb
W8
15 Feb - 21 Feb
W9
22 Feb - 28 Feb
W10
01 Mar - 07 Mar
W11
08 Mar - 14 Mar
W12
15 Mar - 21 Mar
W13
22 Mar - 28 Mar
W14
29 Mar - 04 Apr
W15
05 Apr - 11 Apr
W16
12 Apr - 18 Apr
W17
19 Apr - 25 Apr
W18
26 Apr - 02 May
W19
03 May - 09 May
W20
10 May - 16 May
W21
17 May - 23 May
W22
24 May - 30 May
W23
31 May - 06 Jun
W24
07 Jun - 13 Jun
W25
14 Jun - 20 Jun
W26
21 Jun - 27 Jun
W27
28 Jun - 04 Jul
W28
05 Jul - 11 Jul
W29
12 Jul - 18 Jul
W30
19 Jul - 25 Jul
W31
26 Jul - 01 Aug
W32
02 Aug - 08 Aug
W33
09 Aug - 15 Aug
W34
16 Aug - 22 Aug
W35
23 Aug - 29 Aug
W36
30 Aug - 05 Sep
W37
06 Sep - 12 Sep
W38
13 Sep - 19 Sep
W39
20 Sep - 26 Sep
W40
27 Sep - 03 Oct
W41
04 Oct - 10 Oct
W42
11 Oct - 17 Oct
W43
18 Oct - 24 Oct
W44
25 Oct - 31 Oct
W45
01 Nov - 07 Nov
W46
08 Nov - 14 Nov
W47
15 Nov - 21 Nov
W48
22 Nov - 28 Nov
W49
29 Nov - 05 Dec
W50
06 Dec - 12 Dec
W51
13 Dec - 19 Dec
W52
20 Dec - 26 Dec
W1
27 Dec - 02 Jan
W2
03 Jan - 09 Jan
W3
10 Jan - 16 Jan
TODAY
Stage 0: Strategic Definition
100%
Site Feasibility & Massing Assessment
100%
Client Strategic Brief Approval
100%
Stage 1: Preparation & Briefing
100%
Topographical & Measured Building Survey
100%
Project Brief Freeze & Sustainability Charter
Stage 2: Concept Design
85%
Architectural Concept Drawings & Plans
A-100
90%
Structural & MEP Systems Strategy
S-100
80%
Stage 2 Client Concept Signoff Gate
75%
Stage 3: Spatial Coordination
25%
Spatial Coordination & 3D BIM Model Federation
A-301
30%
Statutory Gate: Planning Permission Submission
10%
Stage 3 Freeze & Design Freeze Milestone
Stage 4: Technical Design
0%
Building Regulations & NBS Chorus Specifications
SPEC-01
0%
Statutory Gate: BSA Gateway 2 Application
0%
Stage 5: Manufacturing & Construction
0%
Main Contractor Site Mobilization & Substructure
0%
Roof Weathertight Envelope & Topping Out
Stage 6: Handover
0%
Practical Completion & Golden Thread Handover
0%
Stage 7: Use
0%